How is the progress of the arrow bar calculated for Agile projects on the Master Schedule?

The Master Schedule for Agile projects is based on Release Tickets and displays their progress rate.

The progress rate of a Release Ticket is calculated from the progress of the Story Points of the tickets directly linked underneath it.

Specifically, the calculation logic is as follows:

Release Ticket Progress(%)=
(Sum of story points for directly linked tickets in"Completed" status) / (Sum of story points for all directly linked tickets) ×100